Published August 12, 2020
WAKEFIELD — This week National Grid crews are continuing to work at three currently active work sites: Montrose Avenue, Salem Street, and Broadway. The work is related to the Woburn-to-Wakefield underground transmission line project.
Duct bank installation is ongoing on Montrose Avenue and Salem Street. The work site on Montrose Avenue is located…