Posted on Tuesday August 2, 2016

LYNNFIELD — The Department of Public Works has scheduled reconstruction of Hidden Valley Road beginning Wednesday, August 3, weather permitting.

Residents along this street will be asked to assist the DPW while this work is occurring. Parking on the street is prohibited while this work is being performed from 6 a.m. until 5 p.m.  The road will be temporarily detoured during this stage of road construction.  Residents along the street should expect delays both entering and leaving their property.

It is recommended that residents and their guests park on Sparhawk Lane during working hours.

If this road work is postponed due to inclement weather, it will proceed on the following work day unless otherwise notified. Those who have any questions may feel free to contact the DPW at 781-334-9500.