Published in the May 21, 2018 edition.
WAKEFIELD — Beginning either today or next Tuesday, May 29, the Town will begin roadway improvements to Vernon Street from Water Street to Salem Street.
The goal is to complete the first phase of the work by June 30 or sooner (weather permitting).
During some of the work phases you will receive updates which will provide more details and schedules.
DPW officials apologize for any inconvenience this may cause.
If you have any questions, please contact Don Schneider, Highway supervisor, at 781-246-6314, or Eric Sherman at 781-246-6308, Monday through Friday, 8 a.m. to 3 p.m.
Please note: there is a five year moratorium on non-emergency roadway excavations once the work is completed.
Thank you in advance for your cooperation
Informational Phase 1
Beginning the week of May 21; planned completion – prior to June 30
Brush clearing
Curbing installation
Handicap Ramp installation
Sidewalk improvements
Phase 2 will be done in the Summer of 2018 or sooner
Milling (removal of 2 inches of bituminous concrete) of the roadway
Repair of roadway structures
Paving
Miscellaneous (traffic markings/loam & seed) as needed
Notes
• During certain phases of the work, no parking will be allowed along the road from 7a.m. to 5 p.m.
• All work is weather permitting. In the case of rain, the schedule will be moved up one day or until the weather clears.