Published in the July 15, 2015 edition
LYNNFIELD — The Lynnfield Center Water District (LCWD) announces that “fire flow” testing and water main flushing of the distribution system will be performed in conjunction with the Lynnfield Fire Department on both Monday, July 20, and Wednesday, July 22 between the hours of 10 a.m. and 3 p.m. This is part of the ongoing hydrological survey project being conducted by the District’s engineering firm CDM Smith.
Many residents will experience discolored water, which should clear after running their cold water at the highest faucet within their house for a short period of time.
Residents are also advised to avoid doing laundry during the flushing period and to check their water after the day’s flushing period before starting their washing machine. If a customer experiences lower pressure at their faucet after the flushing, he or she should check the faucet screen for particles which may have collected and clean out if necessary.
The following is the sequence of hydrants to be flushed:
1. E. Huckleberry Road at Michaels Road
2. End of Thistle Lane
3. 63 Crescent Avenue
4. 56 Parsons Avenue
5. 4 Dianna Circle
6. 94 Essex Street
7. Ashley Court at Marble Hill Drive
8. 12 Chatham Way
9. 26 Wing Road
10. Tapley Road
11. 10 Tophet Road
12. 9 Willis Lane
13. 10 Juniper Road
14. 22 Heritage Lane
15. 35 Edward Avenue
Customers may contact the Lynnfield Center Water District Office at 781-334-3901 or the District’s website, www.LCWD.US, for more information.