MELROSE — The roadway phase of the reconstruction of Lebanon Street will begin on Monday, April 6.
This is a state project, run by the Massachusetts Department of Transportation. City officials have met with state officials, and they have given the town a project calendar with 100 percent completion by October 2015.
On Monday, the reconstruction of the roadway itself will begin at Robinson’s Funeral Home and make its way down Main Street through Hospital Square.
This is a particularly disruptive portion of the project, which will include ongoing detours. There is no plan to shut down the area, however, traffic patterns will be altered. There will be continuous access to the hospital, and at the end of this portion of the project the roadway will be paved. Please take this into account during your travels next week.
APRIL 2015
• Full Depth Reconstruction of Main Street/Green Street/Lebanon Street to East Emerson
• Removal of existing hot mix asphalt
• Removal of trolley tracks
• Roadway re-built from the subgrade materials
• Base and Binder asphalt courses applied
Traffic Signal Work
• Traffic Signal bases, poles, and equipment set
• Working Grove Street and East Foster
MAY 2015
Curbing and sidewalk construction on Lebanon Street from Main Street to Lynde Street. East side (hospital side) of street including side streets
• Removal of existing curbing and sidewalk
• New granite curbing installed
• Sidewalk areas rebuilt with new subgrade materials
• Sidewalk and Driveways formed and poured by DaPonte Construction Corp.
• Curing period of 48 hours
• Driveways paved into existing driveways with hot mix asphalt
Traffic Signal Work
• Traffic Signal bases, poles, and equipment set
• Working Upham Street and East Emerson
Interconnection System
· Wire pulled
Landscaping Work
· Masonry Wall @ 501 Lebanon Street
JUNE 2015
Curbing and Sidewalk Constructio on Lebanon Street from Main Street to Lynde Street (west side), including side streets.
· Removal of existing curbing and sidewalk
· New granite curbing installed
· Sidewalk areas rebuilt with new subgrade materials
· Sidewalk and Driveways formed and poured by DaPonte Construction Corp.
· Curing period of 48 hours
· Driveways paved into existing driveways with hot mix asphalt
Traffic Signal Work
· Traffic signal bases, poles, and equipment set
· Working Main Street and Green Street
Landscaping Work
· Masonry Wall @ 501 Lebanon Street
JULY 2015
Curbing and sidewalk construction on Main Street and Green Street
· Removal of existing curbing and sidewalk including islands
· Granite curbing installation
· Sidewalk areas rebuilt with new subgrade materials
· Sidewalk and Driveways formed and poured by DaPonte Construction Corp.
· Curing period of 48 Hours
· Driveways paved into existing driveways with hot mix asphalt
Traffic Signal Work
· Traffic Signal Service Connections
· Traffic Signal activation
· Existing Traffic Signal Removal
AUGUST 2015
Permanent trench patching on Lebanon Street from Upham Street to East Emerson
· Removing the existing hot mix asphalt trench patch by others
· Replacing the subgrade materials
· Fine grading and compacting materials
· Permanent patch with hot mix asphalt
Traffic Signal Work
· Fully Functioning Traffic Signals
Landscaping Work—Late August
· Loaming and Seeding Lebanon Street from Main Street to Lynde Street- West Side
· Loaming and Seeding Lebanon Street from Main Street to Lynde Street- East Side
· Plantings
SEPTEMBER 2015
Roadway construction
· Micromilling—Lebanon Street-Lynde Street to East Emerson
· Repair any areas of surface with permanent patch
· Adjust Castings to Final Grade in Roadway—Entire Project
· Install New Signage
Misc. Items for Clean Up
Landscaping Work—Early September
· Loaming and Seeding Lebanon Street from Main Street to Lynde Street- West Side
· Loaming and Seeding Lebanon Street from Main Street to Lynde Street- East Side
· Plantings
OCTOBER 2015
Roadway Paving
· Final Top Pavement Course on the Entire Project
Roadway Striping
NOVEMBER 2015
Punch List Items