AN ARTIST’S RENDERING of the planned new Wakefield Memorial High School viewed from Farm Street. The new school would be built on the current site of the Shaun F. Beasley Track & Field. The track and field would be re-built where the old high school currently sits.

By MARK SARDELLA

WAKEFIELD — The Massachusetts School Building Authority (MSBA) Board of Directors voted yesterday to fund a share of the cost of the proposed new Wakefield Memorial High School (WMHS). The MSBA also revised upward its project funding limits, which will mean a boost of approximately $5 million in additional state funds for the WMHS project, bringing the state’s share to about $65 million. The town will still be responsible for about $208 million of the project costs.

Both votes were unanimous.

Yesterday morning’s meeting was held via Zoom. The WMHS project was one on a long list of school build projects at various stages that were on the MSBA’s agenda.

The total cost of a new Wakefield Memorial High School is estimated at $273.7 million. On Oct. 11, Lynn Stapleton of project management firm LeftField, told the School Committee that, of that total, $109,762,737 is eligible for reimbursement by the MSBA.

Based on the funding rate of $360 per square foot in effect at the time, Stapleton said in October that Wakefield could expect a total state reimbursement of about $60 million leaving the town responsible for about $213.7 million.

But the MSBA has been hearing from municipalities that its per-square-foot reimbursement rate of $360 was not coming close to keeping pace with inflation and soaring construction costs. The MSBA board responded yesterday by increasing the effective reimbursement to $432 per square foot.

Based on that increased rate, the MSBA yesterday estimated that Wakefield’s maximum revised grant would be about $65 million. That would leave the town responsible for about $208 million.

MSBA board members stressed that increasing their per-square-foot reimbursement meant that they would be able to fund fewer school projects going forward unless the Massachusetts Legislature steps in and addresses the funding issue.

School Superintendent Doug Lyons and Town Administrator Stephen P. Maio yesterday expressed their appreciation for the MSBA board’s actions in approving funding for the WMHS project.

“We are grateful for the opportunity and the support for the students of Wakefield and generations to come,” Lyons said.

Maio noted that he is a 1980 graduate of Wakefield Memorial High School and his wife and children are all WMHS grads.

“None of us have any angst about building a new school,” he said. “It’s time.”

The Town Council has called a special meeting for today at 12 noon to schedule a Special Town Meeting for Jan. 28 at 9 a.m. in the high school Field House to vote on the town’s share of the funding for the proposed new WMHS project. If the project passes at Town Meeting, it would go before the voters again at a Special Election in March.

Maio said that it was too early to say how the additional $5 million in state funding would impact local taxpayers.

After being rejected for three years in a row, the town learned in December of 2019 that the MSBA Board of Directors had voted to invite Wakefield Memorial High School into the MSBA’s Eligibility Period. The MSBA partners with Massachusetts communities to support the design and construction of educationally-appropriate, flexible, sustainable and cost-effective public school facilities.

In November 2020, Town Meeting voted 200-1 to approve $2 million for a feasibility study for the reconstruction of the high school.

In the spring of 2021, project management firm LeftField was chosen by the Permanent Building Committee to serve as Owner’s Project Manager (OPM) for the WMHS building project. An OPM works as a consultant on behalf of the town through the completion of the project and must be completely independent from the designer, general contractor and any sub-contractors involved in the project at all times.

In August of 2021, the firm of Symmes, Maini & McKee Associates, Inc. (SMMA) of Boston was selected as the designer for the new Wakefield Memorial High School Building Project.

BOND Building was selected in August 2022 as the construction firm that will build a proposed new Wakefield Memorial High School.

In October, new cost estimates placed the total project cost at $273.7 million, up from earlier estimates of $220 million.